With vision, passion and commitment
we carry out projects
and undertake realization
of every task!

Bridge industry project for the task „Design and construction of the Gostyń bypass along the national road No. 12” – in the design and build system.

Design start: 08.2021
Project completion: 03.2023
Scope of the project: 14 bridge structures (2 bridges, 12 viaducts)
Investor: Generalna Dyrekcja Dróg Krajowych i Autostrad Oddział w Poznaniu
Contractor: Lafrentz Polska Sp. z o.o.
Constructor: Mirbud S.A. (consortium leader), Kobylarnia S.A. (consortium partner)
Scope of project : Architectural, construction and technical design of the bridge industry (ZRID decision).

Read more ...

Reconstruction of the bridge in the course of the district road No. 3090P over the Warta River in the town of Ląd

Design completion : 04.2022
Overall lenght : 210,80 m
Deck width: 11,00 m
Span length: 36,00+50,00+44,00+44,00+36,00 m
Construction type: Composite beam structure
Inwestor: Powiatowy Zarząd Dróg w Słupcy
Contractor: Powiatowy Zarząd Dróg w Słupcy
Scope of project : Construction and detailed bridge design, decision on environmental Environmental
conditions, investment location decision, water law permit, construction permit

Read more ...

Construction of a footbridge for cyclists at the bridge over the Bystry Canal in Augustow within the provincial road No. 664 Augustow – Lipsk – in the design and build system

Design completion : 08.2021
Overall lenght: 66,00 m
Deck width: 3,40-3,80 m
Span length: 65,00 m
Construction type: Composite beam structure
Inwestor: Podlaski Zarząd Dróg Wojewódzkich w Białymstoku
Contractor/ Constructor: STRABAG Sp. z o.o.
Scope of project : Multi-branch construction and executive design, workshop design, decision
about environmental conditions, water permit, building permit

Read more ...

Construction of a bridge over the Warta River along with access roads in the course of provincial road No. 431 in Rogalinek.

Design completion : 02.2021
Overall lenght: 202,75 m
Deck width: 15,90 m
Span length: 50,00+100,00+50,00 m
Construction type: Box construction, prestressed, overhang construction.
Inwestor: Wielkopolski Zarząd Dróg Wojewódzkich w Poznaniu
Contractor: SKANSKA S.A.
Scope of project : Executive and technological design

Read more ...

Treetop path

Design start : 04.2019
Design completion : 01.2020
Total lenght : ~250 m
Width : 2,1 m
Construction : wooden
Investor : Miasto Poznań, Zakład Lasów Poznańskich
Contractor/Constructor : Mosty Poznań Sp. z o.o.
Scope of project : Treetop design

The construction and working design was prepared on the basis of an architectural concept prepared by Biuro Projektowe AN-Architekt mgr inż. arch. Adam Nogaj

Read more ...